Northborough's Otis Street sewer main project update for Aug. 2Northborough – Otis Street will continue to be a one-way road going towards Route 9 from the intersection of Thayer/Tomblin Hill Road and Otis Street to Lawrence Street until further notice. Phase 1 of the traffic plan has been implemented. All businesses along Otis Street will remain open for business during construction.

Manhole installation continues from Thayer Street towards Route 9. Northborough police details are on-site to keep traffic flowing as easily as possible.

Most of the residents and business owners in the construction zone have been contacted regarding their septic systems and the installation of sewer laterals to their property lines. If you have not been contacted yet, call Metro Equipment Corporation at 781-843-1330.